Problem Solving (PS) | Re: Six machines, each working at the same constant rate

$
0
0
srkaleem wrote:

Six machines, each working at the same constant rate, together can complete a job in 12 days. How many additional machines, each working at the same constant rate, will be needed to complete the job in 8 days?

A. 2
B. 3
C. 4
D. 6
E. 8

Total work done = 12*6=72 unit
Same work to be done by let n machine in 8 days :
8*n=72 or n=9 machine
Hence extra machine require =9-6=3 nos


Sent from my iPhone usingGMAT Club Forum mobile app
...